|
Helping You Make Your Home Your Castle |
|
|
When to Backfill the Foundation Wall
Backfilling a Foundation
Introduction: A house under construction down the road from where I live had one wall of its concrete foundation walls collapse during backfilling. About forty feet of wall just collapsed into the cellar area about the time it was backfilled to within two feet from the top of the wall.
This was an unfortunate and costly situation that
should have never happened. The DIY homeowner
builder that was performing the backfilling
obviously was not aware that concrete takes a
little longer than two days to harden.
For the DIY homeowner there is a lesson to be
learned about this incident. Portland concrete
begins the process of hardening immediately after
water is combined with the mix but it takes a while
before the chemical reaction is complete. The
chemical reaction continues for several weeks
before it is fully hardened. Wet concrete that is
left to cure in the elements takes approximately
three days to reach about 40% of its designed
strength. After approximately three weeks,
depending on the weather it will reach nearly 75%
of its designed strength. It can take several
months or a few years to get to 100% of its design
strength. Keep in mind that a foundation wall is
usually eight inches thick and eight feet high. It
is a massive piece of concrete to cure.
As far a back filling goes I would not recommend
completely back filling the foundation wall until
the following three events take place.
In the meantime it is alright to partially backfill
the foundation. This really isn’t as much as a show
stopper as one would think because after the forms
have been removed there is still much that must be
done around the exterior of the foundation wall.
The foundation drain system must be installed and
covered with a stone and a mesh and then straw.
This takes a while. After these tasks are complete
partial backfilling can be done to make life a
little easier for the carpenters while they install
the deck (the first floor platform). Partial
backfilling should be limited to three feet until
the deck is on and the foundation floor is poured
if you don’t want risking a foundation wall
collapsing.
Of course in cold weather this whole time line will
slow down because the curing process of the
concrete is slower or may stop completely. In
addition, the vertical steel reinforcing bars could
be installed to further strengthen the foundation
wall much more quickly. This will certainly
increase the cost of the house and that is why it
isn’t or rarely done in residential construction. After everything is said and done the best approach is to be patient and give the concrete time to cure before backfilling. Under most conditions you at least partially backfill it after ten days to a couple of weeks which will give you time to install the foundation drain system. These same considerations should be taken into account when backfilling the retaining wall too.
See more DIY construction
suggestion and ideas
|
|
Home Improvement Plus Perks Copyright©2008